Quick to fix and last for decades
Eternit Profile 6 fibre cement sheets, also known as Big Six, are quick to fix and last for decades but only if the laps, mitres and fixings are right. This guide covers the key steps from the Eternit Profile 6 Fixing Guide, from delivery to the ridge. You can download the full guide at the bottom of this page. For sheet options, sizes and accessories, see our fibre cement roofing sheets page.
All sheets should be fixed in line with BS 8219, and all roof work should follow HSE guidance HSG33 (Health and safety in roof work).
Profile 6 essentials for installers
|
Specification |
Value |
|
Cover width |
1,016 mm (overall width 1,086 mm) |
|
Thickness |
6.7 mm |
|
Corrugation pitch / depth |
146.5 mm / 47.6 mm |
|
Side lap |
70 mm |
|
Minimum end lap |
150 mm |
|
Maximum purlin centres |
1,375 mm |
|
Maximum rail centres (walls) |
1,825 mm |
|
Maximum unsupported overhang |
350 mm |
|
Minimum roof pitch |
5° (maximum slope 15 m, no penetrations) |
|
Fixings |
2 per sheet per purlin |
- Cutting and drilling release dust that can irritate the airways and eyes. Wear eye protection and at least an FFP2 dust mask, as recommended in HSG33.
- Ask us for the Eternit safety data sheet and refer to the COSHH data sheet for full health and safety information.
- Plan safe access and fall protection before anyone goes on the roof, following HSG33.
Before You Start: Delivery, Storage & Stacking
Store sheets as close to the work area as possible, on a firm, level base, raised off the ground on the profiled bearers they were delivered on.
Stack no more than two delivered pallets high. Make a separate stack for each sheet length, or put the longest sheets at the bottom.
Always store sheets smooth (weather) side up. Don't stack pallets of fittings.
Keep stacks out of full summer sun. Uneven heating across the sheets can cause stress and edge cracking.
Store in a ventilated, frost-free space with no risk of condensation. Moisture getting into packs can cause staining, bowing or permanent distortion.
If sheets will stay packed for more than 3 months, store them inside a building.
Natural Grey sheets keep the plastic wrapping on as long as possible. Once a pack is opened or the wrap is damaged, store the sheets under cover.
Coloured sheets: always store under cover, ideally indoors, or under a tarpaulin spaced off the sheets for airflow. Remove the transit wrapping as soon as possible.
Cutting and drilling
Cut at ground level in a well-ventilated area, with the sheet on firm, rigid supports.
Use a handsaw or a slow-speed reciprocating saw. Blades with a 3–3.5 mm tooth pitch work best. Don't use disc or circular saws, and angle grinders are not recommended.
Drill fixing holes with a drill bit made for fibre cement. For larger openings such as flues, use a reciprocating saw or hole saw suitable for fibre cement.
Wipe off all cutting dust straight away with a dry cloth. Left on the sheets, it causes spots and stains.
Check The Roof Structure
Before sheeting starts, check that every purlin and rail is in a true plane, correctly spaced, securely fixed and properly restrained
Profile 6 can be fixed to
- Timber purlins, at least 50 x 75 mm
- Cold-rolled steel, 1.2–3 mm thick
- Hot-rolled steel, over 3 mm thick
Purlins should be at no more than 1,375 mm centres on roofs and rails at no more than 1,825 mm centres on walls.
Laps and sealing: check your exposure first
How much the sheets overlap, and whether the laps are sealed, depends on your roof pitch and how much wind-driven rain the site gets. The UK exposure map in BS 8219 splits sites into two bands, measured in litres of wind-driven rain per square metre per spell. Buildings that stand above their surroundings, sit in open country with no windbreaks, or are on or near the coast or a hilltop should be treated as severely exposed. For the Highlands and Islands, contact Eternit's technical team.
Sheltered and moderate sites (less than 56.5 l/m² per spell)
|
Minimum roof pitch |
End lap length |
End lap treatment |
Side lap treatment |
|
22.5° and over |
150 mm |
Unsealed |
Unsealed |
|
15° and over |
300 mm |
Unsealed |
Unsealed |
|
15° and over |
150 mm |
Sealed |
Unsealed |
|
10° and over |
150 mm |
Sealed |
Sealed |
|
5° and over |
300 mm |
Double sealed |
Sealed |
Moderate and severe sites (56.5 l/m² per spell or more)
|
Minimum roof pitch |
End lap length |
End lap treatment |
Side lap treatment |
|
25° and over |
150 mm |
Unsealed |
Unsealed |
|
17.5° and over |
150 mm |
Sealed |
Unsealed |
|
15° and over |
150 mm |
Sealed |
Sealed |
|
10° and over |
300 mm |
Sealed |
Sealed |
|
5° and over |
300 mm |
Double sealed |
Sealed |
Low pitches: between 5° and 10°, keep slopes to 15 m maximum, with double-sealed end laps and sealed side laps.
Snow: on roofs over 10° where parapets could let snow build up, use 300 mm double-sealed end laps and sealed side laps.
Need sheets, fittings or advice?
Tinman Steels has been supplying roofing from Tamworth since 1987. We supply Eternit fibre cement roofing sheets with all the ridges, closers, rooflights, fixings and sealants you need to finish the job. Call 01827 286340
Origin Story
Start at one end of the building at eaves level and work up in vertical tiers, one sheet wide, from eaves to ridge. End laps should form one continuous straight line from gable to gable, never staggered, and side laps should line up from eaves to ridge.
On a duo-pitch roof, start both slopes from the same end of the building, so one slope is laid left to right and the other right to left. The corrugations must line up at the apex or the ridge fittings won't fit.
The corrugation on one edge of each sheet is lower than the others. That edge must always be the underlap.
Where side and end laps meet, four sheet thicknesses would build up. To stop this, two of the four sheets at each junction are mitred so they sit flat.
- Cut the mitre from a point 150 mm up the side edge (or the depth of your end lap) to a point 70 mm along the end edge.
- Leave a gap of 3–6 mm between the mitred corners. Avoid box mitres.
- Cut mitres on the ground, never in place on the roof.
Working left to right, the first sheet at the eaves is not mitred. Sheets above it are mitred bottom right. In the following tiers, the eaves sheet is mitred top left, middle sheets top left and bottom right, and the ridge sheet bottom right. In the last tier at the right-hand edge, sheets are mitred top left only, and the final sheet at the ridge is not mitred. When laying right to left, the mitres are on the opposite corners. The full guide includes a numbered mitring plan.
- Use a pre-formed 8 mm butyl or polyisobutylene sealing strip, as recommended in BS 8219. Gun-grade sealants are not suitable.
- Make sure the sheet surface is free of dust and grease. Lay the strip without stretching it, following the corrugations across the sheet.
- Place the top sheet in its final position first time, because it can't be slid once it touches the sealant. Press it down firmly before fixing.
- For double-sealed 300 mm end laps, place the second strip 100–200 mm below the fixing.
- Any fibre cement fittings used with the sheets need the same lap sealing.
- Sealing strip is easier to work when warm, so keep it somewhere warm in cold weather.
- Use 2 fasteners per sheet per purlin, no more and no less.
- Place fasteners on the first full corrugation next to the side lap, and 50 mm from the top of the end lap.
- Self-drilling, self-tapping Topfix fasteners are normally used. They drill an oversize hole through the sheet and tap into the purlin.
- Use a power tool with an adjustable depth setter so the washers seat correctly, and fix perpendicular to the roof plane.
- On timber purlins, keep fixings at least five times the fixing diameter from the edge of the timber to avoid splitting (BS 5268).
- Sealant and some insulated build-ups can settle, so check and retighten all fixings at the end of the job.
|
Topfix fastener |
Purlin |
Size |
|
Carbon steel |
Timber |
6.5 x 130 mm |
|
Stainless steel |
Timber |
6.5 x 130 mm |
|
Carbon steel |
Steel |
6.3 x 105 mm |
|
Stainless steel |
Steel |
6.3 x 120 mm |
Eaves, ridges and verges
Eaves closers and fillers
Eaves closers and fillers seal the corrugations at the eaves. They match the 1,016 mm sheet cover and work whether you lay left to right or right to left. Fix them to the eaves beam or bottom purlin with the sheet fasteners.
Cranked crown ridges and vents
- Available in 750, 900 and 1,800 mm girths, in pitches from 10° to 22.5°, to suit roofs from 8.5° to 23.25°.
- 750 mm and 900 mm cranked crowns and vents must lap onto the sheets by 300 mm to form a non-fragile detail.
- Both the cranks and the top sheets must be mitred, and both slopes must be sheeted from the same gable with aligned corrugations.
- Fix at least 100 mm up from the tail of the crown where the sheets have 150 mm end laps, or 250 mm up where they have 300 mm end laps.
- Where 750 mm crowns are used on 15°–22.5° pitches, use 8 mm butyl strip as a spacer between the ridge and the sheet.
The full guide includes purlin setting-out tables for each crown size, pitch and purlin depth.
Two-piece ridges
Two-piece ridges suit pitches from 10° to 45° and come in close fitting, ventilating, plain wing and northlight versions. Sheets should lap at least 200 mm under the ridge, and ridges are fixed through the sheets into the top purlin. Laying the small roll on the left-to-right slope lines up the ridge laps with the sheet laps. Where lap sealant is used on the sheets, apply it to close-fitting and northlight ridges too. Disc finials finish the ridge ends and should be bolted to the inner roll before the outer roll goes on.
Bargeboards
- The sheets should run at least two crest corrugations under the bargeboard.
- Fix through the sheets into the purlins and into the wall or cladding, with fixings at no more than 750 mm centres.
- Position bargeboard laps directly below the sheet end laps.
- On brick or block gables, keep the bargeboard 25 mm clear of the wall face.
- Verges take the most wind load, so add extra fixings, especially at the ends of each bargeboard.
Apron flashings
Apron flashings finish the top of a roof where it meets a wall, with a lead flashing dressed into the wall and over the apron. When sheeting left to right, the apron laps line up with the sheet laps. When sheeting right to left, offset them by one corrugation.
Ventilated roofs for livestock buildings
Profile 6 suits three ventilation systems for agricultural buildings. Get professional advice on the ventilation gap you need for the number of animals housed.
- Open ridges (protected or unprotected): for pitches from 10° to 22.5°. To meet HSG33, the gap between apex purlins should be no more than 300 mm, so the ventilation gap is limited to 250 mm.
- Breathing roofs: a preservative-treated 50 x 25 mm timber batten is fitted between the sheets at each end lap, with a 150 mm lap and purlins at no more than 1,375 mm centres. Increase laps to 300 mm on exposed sites.
- Spaced roofs: Profile 6 sheets trimmed to 1,000 mm wide are laid with a 15–25 mm gap between runs. Fit a soaker or DPM under each gap to protect the purlins. Sheets fixed this way are classed as a fragile roof covering.
Movement joints on long buildings
BS 8219 recommends movement joints on roofs and walls of buildings over 45 m long, and wherever the building has its own structural movement joints.
|
Length of building |
Movement joints needed |
|
Up to 45 m |
None |
|
45–75 m |
1 |
|
75–105 m |
2 |
|
Over 105 m |
1 extra for every additional 30 m |
To form a joint, cut each sheet through the valley at its centre and space the two halves 25–30 mm apart. Fix the movement joint piece with one fixing per purlin through the gap, and don't overtighten it. Buildings with high humidity or sudden temperature changes may need joints closer together.
Fitting GRP rooflights
Eternit Agrisheet GRP rooflights are made to fit Profile 6. They are classed as non-fragile Class C (ACR[M]001:2014) when new and fully fixed to Eternit's recommendations.
- Support the rooflight at each purlin with profile filler blocks, eaves closers or the Profile 6 sheet.
- Rooflights aren't mitred, and the matching corner of the neighbouring fibre cement sheet should be left unmitred too.
- Fix through every corrugation except the side laps, using the same fasteners as the sheets in oversize holes.
- Stitch side laps at 300–400 mm centres with self-sealing fasteners or seam bolts with wide washers.
- Seal end and side laps with 10 mm butyl strip.
Need rooflights for another roof profile? See our GRP rooflights page.
Download the full installation guide
The full guide includes detailed drawings, the UK exposure map, the mitring plan and purlin setting-out tables for ridges.
Frequently asked questions
For Eternit Profile 6 it's 5°, with a maximum slope length of 15 m and no penetrations. Between 5° and 10°, use double-sealed 300 mm end laps and sealed side laps.
It depends on your roof pitch and site exposure. Steep roofs on sheltered sites can often be left unsealed, while low-pitch or exposed roofs need sealed or double-sealed laps. Check the tables above.
Two fasteners per sheet at every purlin, placed on the first full corrugation next to the side lap.
Where four sheets meet, mitring two of them stops four thicknesses building up, so the sheets lie flat and the joint stays weathertight.
At ground level, with a handsaw or slow-speed reciprocating saw, wearing at least an FFP2 mask. Don't use angle grinders, and wipe away the dust straight away.
On buildings over 45 m long: one joint for 45–75 m, two for 75–105 m, and one more for every extra 30 m.